Converting to Three-P­hase Power

In most cases, it is possible to convert the connection from single-phase to three-phase. The fee for this conversion can be found in the connection fee price list.

Process for Converting from Single-Phase to Three-Phase Power

  1. Hire a Certified Electrician: Contact a certified electrician to carry out the work.

  2. Service Request: The electrician submits a service request to Veitur through the Construction Authority (Húsnæðis og mannvirkjastofnun).

  3. Delivery Time and Cost Information: The contact person is informed about the delivery time and any associated costs.

  4. Power Disconnection: Veitur disconnects the power in consultation with the electrician.

  5. Modification of Electrical Panel: The electrician removes the single-phase meter and modifies the electrical panel.

  6. Installation of Three-Phase Power: Veitur converts the power supply to three-phase and installs a new meter.

Delivery Time: The estimated delivery time for very simple changes is 5 working days, provided that the cable is suitable for three-phase power and no changes or upgrades to the street cabinet are necessary.

See the pricelist for more information about costs.