In most cases, it is possible to convert the connection from single-phase to three-phase. The fee for this conversion can be found in the connection fee price list.
Process for Converting from Single-Phase to Three-Phase Power
Hire a Certified Electrician: Contact a certified electrician to carry out the work.
Service Request: The electrician submits a service request to Veitur through the Construction Authority (Húsnæðis og mannvirkjastofnun).
Delivery Time and Cost Information: The contact person is informed about the delivery time and any associated costs.
Power Disconnection: Veitur disconnects the power in consultation with the electrician.
Modification of Electrical Panel: The electrician removes the single-phase meter and modifies the electrical panel.
Installation of Three-Phase Power: Veitur converts the power supply to three-phase and installs a new meter.
Delivery Time: The estimated delivery time for very simple changes is 5 working days, provided that the cable is suitable for three-phase power and no changes or upgrades to the street cabinet are necessary.
See the pricelist for more information about costs.